A draw schedule is the plan for releasing money in stages during a rehab: when each payment is due, what work must be finished first, and how much goes out. On a flip you usually have two running at once. Your lender releases funds to you, and you pay your contractor and suppliers. When the two drift apart, you end up fronting cash or paying for work that was never funded.
This guide explains both schedules, shows a sample, and covers the one habit that keeps them honest: tracking what each draw was supposed to cover against what you actually spent.
Key Takeaways
- A fix and flip draw schedule releases rehab funds in stages, usually after the lender verifies the work is done.
- You have two schedules: lender draws to you and your payments to the contractor. Track both.
- Each draw can cost $200 to $300 in inspection fees, and funds take days to arrive, so cash timing matters.
- The lender’s schedule covers your budget, not your overruns. Overruns come out of contingency or your cash.
- Compare cumulative draws with cumulative spend after every draw. The gap is your float.
Two draw schedules on every flip
The lender’s draw schedule governs when you receive money. If your loan includes a rehab holdback, the lender releases it in installments as work is completed, not all at closing.
The contractor’s payment schedule governs when you pay out. Contractors are usually paid in stages tied to milestones. One contractor payment guide describes 4 to 6 progress payments with 5% to 10% held back until the punch list is finished, each exchanged for a signed lien waiver (EZ Estimates).
If you pay cash with no loan, only the second schedule exists. If your contractor is paid directly by the lender, the first one matters most. Either way, the schedule is a plan, and your records show whether reality is following it.
How a lender draw schedule works
Lenders tie draws to milestones and verify the work before releasing money. One construction lender puts typical residential projects at 4 to 6 draws, with an inspector confirming each milestone before funding (Ledger). Flip loans vary by lender, so read your own loan agreement for the exact process.
Three details affect your profit more than the schedule’s shape:
- Timing. The same lender quotes 2 to 5 business days for the inspection and 2 to 3 business days to fund after approval. Your contractor can finish a stage and wait roughly a week or more for the draw.
- Fees. Draw and inspection fees run $200 to $300 per disbursement, so five or six draws add $1,000 to $1,800 (Simplending Financial). Fewer, larger draws cost less in fees but give you less flexibility.
- Interest. Some lenders charge interest only on money actually drawn. Others use Dutch interest, which charges on the full approved loan from day one, including undrawn rehab funds (Simplending Financial). Ask which applies, because it changes your carrying cost. See house flip holding costs and how to estimate them.
A sample draw schedule
A simple renovation loan example from one lender has four draws on a $50,000 budget: $5,000 at closing, $12,500 after floors are done, $17,500 after cabinets, and $15,000 after countertops, or 10%, 25%, 35%, and 30%. The lender notes that every draw should come with receipts (Cincinnati Federal).
Here is an illustrative schedule for a flip with a $45,000 rehab budget and five draws:
- Draw 1, demo and structural repairs (15%): $6,750
- Draw 2, plumbing, electrical, and HVAC rough-in (25%): $11,250
- Draw 3, drywall and flooring (25%): $11,250
- Draw 4, kitchen and baths (25%): $11,250
- Draw 5, final finishes and punch list (10%): $4,500
The shape is front-loaded on structure and trades, with the last draw held until the punch list is closed, the same way a contractor’s retainage works. Your own percentages should follow your scope and your lender’s rules.
Track the schedule against what you actually spend
A draw schedule is built from a budget. It does not know about the change order you approved in week three. So after every draw, compare two running totals:
- Cumulative draws received. What the lender has released.
- Cumulative spend. What you have paid contractors, suppliers, and permits, including signed commitments.
The difference is your float, the cash you are carrying until the next draw. In the example, by Draw 3 the lender has released $29,250 in total, but you have actually spent $33,400, so you are fronting $4,150. By the end, the schedule has released the full $45,000 while spend reached $50,800, a $5,800 overrun the schedule never covered.
That gap is the same overrun you track in budget versus actual on a house flip. The draw schedule tells you when cash arrives. Budget versus actual tells you whether the cash will be enough.
Draw-day checklist
- Photograph the completed work before requesting the draw, and keep the photos with the request.
- Gather receipts and invoices for everything in the stage. Lenders expect them. See scanning receipts to log rehab costs.
- Collect lien waivers from the contractor and subcontractors when you pay them.
- Log signed change orders the day you sign them, so spend includes commitments, not only paid bills.
- Request early. Inspection and funding take days, so ask for the draw as the stage nears completion, not after the crew is waiting.
- Do not pay ahead. Pay the contractor for finished work, not for the next stage, unless your contract says otherwise and you can carry the cost.
For how to log each of these entries so nothing is counted twice, see how to track house flip expenses without the spreadsheet mess.
Frequently asked questions
What is a draw schedule?
A draw schedule is a plan for releasing rehab or construction money in stages. It lists each stage, the work that must be complete, and the amount released. On a flip it can describe the lender’s draws to you, your payments to the contractor, or both.
How many draws does a fix and flip loan have?
It varies by lender and scope. One construction lender puts typical residential projects at 4 to 6 draws, and a short cosmetic rehab may have fewer. Check your loan agreement for the number and for any limit on draw requests.
How long does it take to get a draw?
One lender quotes 2 to 5 business days for the inspection and 2 to 3 business days to fund after approval, so a week or more is realistic. Plan your contractor payments around that delay, and request each draw before the stage is fully done.
What does each draw cost?
Draw and inspection fees run $200 to $300 per disbursement according to one lender, which adds $1,000 to $1,800 across five or six draws. Fees differ by lender, so ask for the full fee schedule before you close.
Keep the schedule and the spend in one place
A draw schedule is a plan for cash. Your records show whether the plan matches the job. After each draw, compare cumulative draws with cumulative spend, include signed change orders, and watch the float. That is the habit that catches an overrun at Draw 3 instead of at closing.
For the formula underneath all of this, see house flip profit tracking, stage by stage.
This article is for education, not financial or investment advice. Loan terms, fees, and draw rules vary by lender; confirm them in your own loan agreement.
About the author — Albert Chui. Albert Chui is a real estate investor in the San Gabriel Valley, California, who has flipped roughly 80 houses in the area since 2021. He ran those projects on spreadsheets at first, and learned firsthand how contractor changes, delays, and mid-rehab overruns quietly turn a profitable deal into a thin one. He founded FlipMargin so flippers can see current costs and projected profit throughout a rehab, not just at closing.